Ahmedabad, May 4 (IANS) Five heavy portal beams for the Mumbai-Ahmedabad Bullet Train project have been launched over the Ahmedabad-Vadodara railway line in the Maninagar area of Ahmedabad, completing a critical phase of construction within a month. The precast-prestressed beams were launched in a planned sequence on April 8, 13, 19, 24, and 29, with the entire operation completed within 22 days in coordination with Indian Railways.Each installation was carried out in approximately three and a h…
Latest Mumbai-Ahmedabad Bullet Train Project News & Updates
Ahmedabad, April 8 (IANS) The Mumbai‑Ahmedabad Bullet Train project reached a major engineering milestone on Wednesday, with the successful launch of one of its heaviest precast‑prestressed portal beams on the Ahmedabad‑Vadodara railway line in the Maninagar area, officials said. The portal beam, a precast concrete structure weighing nearly 1,360 metric tonnes, measures 34 metres in length with a cross‑section of 5.5 metres by 4.5 metres.Officials said that a total of five such b…