Close Menu
  • Indian Festivals 2026
  • Movie & OTT Releases This Week
  • News
  • Entertainment
  • NRI Life
  • Research
  • Advertise with us
Facebook X (Twitter) Instagram YouTube
  • Download Indian Community App
  • Advertise Here
Facebook X (Twitter) Instagram
Indian CommunityIndian Community
Trending
  • Operation Safed Sagar Review 2026: A Powerful Tribute To Kargil’s Air Warriors
  • DC Movie Review 2026: Wamiqa Gabbi’s Fierce Performance Make This Saga a Massive Triumph
  • Korean Kanakaraju Movie Review 2026: An Unmissable Cross-Border Ride
  • Ohh My Dog Movie Review 2026: A Heartwarming Triumph Of Loyalty & Love
  • G.D.N. Movie Review: Madhavan’s Powerhouse Biopic Is a Tribute to India’s Forgotten Edison
  • Adhey Neevu Adhey Nenu 2026 Movie Review: A Love Triangle That Hides a Deadly Secret
  • Hanuman Ansh 2026 Movie Review: A Soul-Stirring Tribute That Will Move You to Tears
  • Karmakhya 2026 Movie Review: Samuthirakani’s Brilliant Performance Powers This Thriller
  • Indian Festivals 2026
  • News
    • National
    • International
    • Entertainment
    • Achievements
    • Scam Alerts
    • Business
    • Health & Medicine
    • Science & Technology
    • Sports
  • Entertainment
  • Latest Movie Releases
    • Latest OTT Releases
  • NRI Life
  • India & Culture
  • Health & Wellness
  • Research
Indian CommunityIndian Community
Home » News » National
National

Rajasthan: Dungarpur-Ratlam rail project gains pace with 646 hectares acquired

Indian Community Editorial TeamBy Indian Community Editorial TeamAugust 7, 20262 Mins ReadNo Comments Add us to Google Preferred Sources
Rajasthan: Dungarpur-Ratlam rail project gains pace with 646 hectares acquired
Share
Facebook Twitter LinkedIn Pinterest Email

Jaipur, Aug 7 (IANS) The 189‑km Ratlam‑Banswara‑Dungarpur new railway line project, sanctioned at an estimated cost of Rs 2,083 crore, is progressing with 646 hectares of land acquired out of the 1,736 hectares required, Union Railway Minister Ashwini Vaishnaw informed the Rajya Sabha in a written reply on Friday.

The project is being executed on a 50:50 cost‑sharing basis between the Ministry of Railways and the Rajasthan Government, with the state responsible for providing land free of cost. An expenditure of Rs 243 crore had been incurred on the project till March 2026, the Minister said.

To further strengthen rail connectivity in the Banswara region, the Railways has also sanctioned a Detailed Project Report (DPR) for the proposed 380‑km Nimach‑Banswara‑Dahod‑Alirajpur‑Nandurbar new railway line. The project will be considered for sanction after completion of the DPR and consultations with stakeholders, including the concerned state governments, NITI Aayog and the Ministry of Finance.

Vaishnaw said Rajasthan has witnessed a significant increase in railway infrastructure investment in recent years. The state’s railway budget allocation has risen from an average of Rs 682 crore annually during 2009‑14 to Rs 10,228 crore in 2026‑27, nearly 15 times higher. Railway track commissioning has also accelerated, with 3,886 km of new track commissioned between 2014 and 2026, averaging 324 km per year, compared with 798 km at an average of 160 km annually during 2009‑14.

As of April 1, 2026, a total of 32 railway infrastructure projects, including 15 new lines, five gauge conversion projects and 12 doubling projects, covering 3,447 km and involving an investment of Rs 47,498 crore, are under implementation in Rajasthan. Of these, 1,322 km have been commissioned, and Rs 23,245 crore has been spent up to March 2026.

The Minister said several railway projects have recently been completed in Rajasthan, including the Bina‑Kota doubling, Dausa‑Gangapur City doubling, Phulera‑Degana doubling, Alwar‑Bandikui doubling and Jaipur‑Churu gauge conversion.

Major ongoing projects include the Pushkar‑Merta, Taranga Hill‑Abu Road, Ramganjmandi‑Bhopal, Sawai Madhopur‑Jaipur doubling, Luni‑Bhildi doubling and the Nagda‑Mathura third and fourth line projects.

Vaishnaw noted that the timely completion of railway projects depends on factors such as land acquisition, forest and statutory clearances, shifting of utilities, geological conditions, law and order and the working season available at project sites.

The information was provided by Union Minister for Railways, Information & Broadcasting and Electronics & Information Technology Ashwini Vaishnaw in a written reply in the Rajya Sabha.

–IANS

arc/dan

Add us to Google Preferred Sources
Indian Community Editorial Team

The Indian Community Editorial Team curates, verifies, and publishes stories that matter to Indians worldwide. From culture and community to business and innovation, our mission is to spotlight voices, ideas, and events that bring our global community closer together. Have news or a story to share? Submit it to us at [email protected].

Add A Comment

Sunny Deol meets UP CM Yogi Adityanath

August 7, 2026

Jr Boys' NFC: Dr BC Roy Trophy to kick off in Bengaluru, Narainpur on August 25

August 7, 2026

Cop deployed outside Salman Khan’s house collapses, dies

August 7, 2026

Football: Ex-Getafe defender Duarte joins Sao Paulo on free transfer

August 7, 2026
  • Facebook
  • Twitter
  • Pinterest
  • Instagram
About Us
  • About Us
  • Contact Us
  • Terms of Service
Corporate
  • Download Indian Community App
  • Advertise Here
Facebook X (Twitter) Instagram
  • About Us
  • Contact Us
  • Terms of Service
© 2026 Designed by CreativeMerchants.

Type above and press Enter to search. Press Esc to cancel.